Hub Settlement vs. Nodal Settlement (Energy Markets)

I understand basis risk on a high level, but i dont understand why is hub settlement bad for developers and good for offtakers. 

I understand concept of nodal prices and why they are typically lower and more volatile than hub 

i understand ppa contracts can have hub sttlment or nodal settlement clause...but what confuses is me is like who is paying who, how and why is the developer or offtaker getting exposed to this kind of basis risk...

developer gets electricity revenue at the nodal rate, but then also has to pay up some thing at the hub, why are the payments / settlements happening twice...so fucking lost  

could some kind soul please explain to me?

 

Based on the most helpful WSO content, let's delve into the complexities of Hub Settlement versus Nodal Settlement in energy markets, particularly focusing on why hub settlement might be unfavorable for developers and favorable for offtakers.

  1. Hub Settlement vs. Nodal Settlement:

    • Hub Settlement: In hub settlement, transactions are settled at a common pricing point known as the 'hub'. This is a predefined location or average of locations and is generally less volatile due to the aggregation of prices over a wider area.
    • Nodal Settlement: In nodal settlement, prices are determined at numerous specific locations or nodes within the grid. These prices can vary significantly due to local supply and demand conditions, leading to higher volatility.
  2. Understanding Basis Risk:

    • Basis risk arises from the difference between the hub price and the nodal price. This risk is a critical factor for both developers and offtakers when they enter Power Purchase Agreements (PPAs) that specify either hub or nodal settlement.
  3. Impact on Developers and Offtakers:

    • Developers: Typically, developers receive revenue based on the electricity prices at the node where their generation assets are located. If a PPA is based on hub settlement, the developer is exposed to the risk of the difference between the nodal price (where they generate electricity) and the hub price (settlement price in the PPA). This can lead to losses if the nodal price is consistently lower than the hub price.
    • Offtakers: Offtakers (like utilities or large consumers) prefer hub settlement because it offers more predictable prices and reduces their exposure to the high volatility of nodal prices. They benefit from the aggregation and smoothing effect of the hub price.
  4. Why Double Payments/Settlements?:

    • In scenarios where there is a discrepancy between the hub and nodal prices, and a PPA involves hub settlement, the developer might need to 'true-up' or compensate for the difference. Essentially, the developer receives payment based on the nodal rate but has to settle any discrepancies at the hub rate, leading to a form of double financial engagement – receiving at one rate and potentially paying out at another.
  5. Developer's Challenge:

    • The challenge for developers is managing this basis risk effectively. They need to predict or hedge against significant differences between nodal and hub prices to avoid financial losses.

Understanding these dynamics is crucial for both developers and offtakers to negotiate PPAs that align with their risk management strategies and financial goals. This explanation should provide a clearer picture of the financial flows and risks involved in hub and nodal settlements in energy markets.

Sources: Q&A: Director of Energy Trading, Q&A: Director of Energy Trading, Q&A: Non-Target School to Portfolio Manager at a Top Hedge Fund – 6 Years Out of Undergrad, Physical Energy Trading And Logistics, Breaking into Oil & Gas / Energy as a UG

I'm an AI bot trained on the most helpful WSO content across 17+ years.
 
Most Helpful

Sure. So up front, PPA is almost always a “virtual” PPA, aka financial swap. Offtaker pays developer/project owner a fixed amount per MWh, and receives the floating price. There are nuances and exceptions to all of this, but 95% of the time this is the starting point. The project only factors in to determine the volume during each settlement period, almost always hourly. And end of month these hourly settlements are summed, and one party owes the other some amount.
So the offtaker wants the floating price to be high, and from their perspective thats where it ends.

For the developer, the PPA is a hedge. The project will sell into the grid at the floating price (will come back to nodes in a second). If prices are high, they lose on the PPA, but the project makes more money, so it should net out to the PPA price (do some simple back of the envelope examples).

Now to nodes vs. hubs. The project will get paid the nodal price. This is a function of the physical grid and market regulations, theres nothing that can be done to avoid this (except doing other financial power market machinations to obtain other payments). But as you know, nodes are volatile. And if its a big project, in a remote location, it will affect the nodal price by oversupplying that part of the grid, driving down the price relative to other nodes.

Hubs are just weighted averages of many nodes. So the individual node price movements are smoothed out, and because of that, they are price benchmark for any futures product participants can use to hedge/speculate with.

So the developers would love to settle the PPA contract at the node, and offtakers don’t because any hedge they do with a hub settled futures product is diluted, and they’re exposed to those potentially lower node prices, when they want high prices. So why don’t developers typically get their way but offtakers do? Its just negotiating power. There are more developers and projects looking for offtakers than there are offtakers, so offtakers dictate many of the terms. Another big consideration here is that almost always a PPA is being negotiated before the project is built, and built at a new node. So no historical data to reference. And doing long-term grid modeling at the nodal level is incredibly time consuming and expensive, and a total crapshoot. So is long term hub modeling, but its more reliable to make higher level assumptions at the zonal level and average certain things out, and get a hub price forecast that is somewhat defensible. Developers will pay to do nodal studies, because they care and have the time, but your typical corporate buyer will have neither the time or money or knowledge to even discern a good nodal consultant. Utility offtakers are a bit of an exception because they will have nodal risk, nodal studies, know the grid, etc. But getting a good utility offtaker is hard for various reasons.

The developers never pays anything at the hub under the PPA, they get paid the hub price by the offtaker. But payments do happen twice - the project gets paid the nodal price as dictated by the grid, and then the PPA settlement happens bi-laterally. The grid operator who sets prices has no knowledge of the PPA nor do they care (they actually do but thats not relevant for this).

PPAs are done to give developers revenue certainty, and revenue to protect them in case grid prices go down and they can’t afford to pay back the initial capex of the project. What offtakers get is more varied. For renewables, they get credits and marketing “rights” to say they funded green energy. It can also be a hedge if they have wholesale power demand in the area. They may be mandated to fund new energy builds if they’re a utility or a large energy user mandated by the utility. They may be a more speculative entity who is looking for upside volatility as a hedge to a short energy portfolio or just a way to get cheaper upside exposure than current futures prices. Thats a small percentage of the market though. 95% is corporates for “green” reasons or utilities for green reasons. PPAs are much less common in non renewable projects.

Hopefully this helps. Curious what your interest stems from, since its a pretty small industry. Feel free to DM me if you want.

 

Thanks so this much. This was very helpful.

It becomes confusing to keep track of who gets paid what, when, and why. To your comment, from a developer’s perspective, do I have the payment mechanisms and logic correct?  

“The developers never pays anything at the hub under the PPA, they get paid the hub price by the offtaker. But payments do happen twice - the project gets paid the nodal price as dictated by the grid, and then the PPA settlement happens bi-laterally“

Let’s stay my PPA price is fixed $30/mwh and its energy-only. And we’re talking just 1 MWh of output. for this example, Nodal price is $20/mwh and hub-profile adjusted price is $22/mwh.

Step 1: I (IPP) first get paid $20/Mwh for injecting into the grid

Step 2: And then I pay the offtaker ($22/mwh) to settle because the settlement is supposed to be hub-based, so I pay the offtaker $2 additional because the hub price is 22 ?

Step 3: The offtaker then pays me $30 / mwh

And so my final energy price is $28/Mwh instead of $30?

I recently joined an IPP in its development team looking after the investments evaluation part

 

That is correct, for a given time period, such as an hour. Steps 2 and 3 can happen in either order. In reality, that final settlement amount of $28 is kept as a running total for a month (or a quarter in some cases), and then payments are actually made. So the grid operator will facilitate the payment of the $20, and the offtaker will facilitate their payment of $8 to the IPP. 

 

Thank you. I have gone through ercot’s training webinars, primers by equity research analysts; and tax equity related content (modeling and otherwise) 
any book or guide that you think is a must read? I feel my knowledge regarding interconnection / engineering,  market designs and energy risk mgmt can def improve 

I’ve been in this space for 18 months now and would like to move to infra investing in another 6 months so trying to soak as much knowledge as I can 

I really appreciated your thoughtful response 

 

Praesentium sint sed maiores placeat praesentium incidunt. Quidem voluptatem quod ex est autem quis animi perspiciatis. Rerum explicabo ut repellat suscipit explicabo molestias numquam voluptate. Sit cumque neque expedita.

Et omnis voluptas ut dolorum dolorum nulla. Enim culpa molestiae beatae officiis est exercitationem aut.

Sequi suscipit quia incidunt ea laudantium eligendi. Rerum est ut dolores architecto rerum ratione dolorem officiis. Distinctio dolor possimus sapiente.

Career Advancement Opportunities

May 2024 Investment Banking

  • Jefferies & Company 02 99.4%
  • Lazard Freres No 98.8%
  • Harris Williams & Co. 25 98.3%
  • Goldman Sachs 17 97.7%
  • JPMorgan Chase 04 97.1%

Overall Employee Satisfaction

May 2024 Investment Banking

  • Harris Williams & Co. 18 99.4%
  • JPMorgan Chase 10 98.8%
  • Lazard Freres 05 98.3%
  • Morgan Stanley 07 97.7%
  • William Blair 03 97.1%

Professional Growth Opportunities

May 2024 Investment Banking

  • Lazard Freres 01 99.4%
  • Jefferies & Company 02 98.8%
  • Goldman Sachs 17 98.3%
  • Moelis & Company 07 97.7%
  • JPMorgan Chase 05 97.1%

Total Avg Compensation

May 2024 Investment Banking

  • Director/MD (5) $648
  • Vice President (21) $373
  • Associates (91) $259
  • 3rd+ Year Analyst (14) $181
  • Intern/Summer Associate (33) $170
  • 2nd Year Analyst (68) $168
  • 1st Year Analyst (205) $159
  • Intern/Summer Analyst (146) $101
notes
16 IB Interviews Notes

“... there’s no excuse to not take advantage of the resources out there available to you. Best value for your $ are the...”

Leaderboard

1
redever's picture
redever
99.2
2
BankonBanking's picture
BankonBanking
99.0
3
Betsy Massar's picture
Betsy Massar
99.0
4
Secyh62's picture
Secyh62
99.0
5
GameTheory's picture
GameTheory
98.9
6
CompBanker's picture
CompBanker
98.9
7
dosk17's picture
dosk17
98.9
8
kanon's picture
kanon
98.9
9
Linda Abraham's picture
Linda Abraham
98.8
10
bolo up's picture
bolo up
98.8
success
From 10 rejections to 1 dream investment banking internship

“... I believe it was the single biggest reason why I ended up with an offer...”